The London Landmarks Half Marathon brings together more than 20,000 runners, requiring specialist collaboration and extensive coordination. With a route passing through Westminster and the City of London, more than 200 road closures were implemented, each supported by appropriate protective security measures.
Following a security assessment, Westminster Bridge, Parliament Square and Tower Bridge were identified as priority locations requiring enhanced hostile vehicle mitigation (HVM). Hill & Smith Infrastructure worked in partnership with BUKO Traffic & Safety to identify and deploy an impact-rated solution that could provide the required protection while minimising disruption to London’s busy road network.
Westminster Bridge, Parliament Square and Tower Bridge were identified as areas requiring a more robust HVM solution. Each location presented different spatial and operational requirements, meaning the proposed layouts needed to consider site measurements, available space and the anticipated direction of vehicle attack.
The solution also had to be deployed within a tightly controlled programme. To minimise disruption, it was imperative that roads remained open for as long as possible before the event and reopened promptly afterwards. This left a limited timeframe to assemble, transport and deploy the HVM across three separate locations. Concurrently, the solution had to incorporate emergency access points without compromising the wider protective security arrangements.
The BUKO Traffic & Safety deployment team worked closely with Shaun Bentley, General Manager HVM & Perimeter Security at Hill & Smith Infrastructure, to determine the most appropriate solution for the three priority locations. Using detailed site measurements, the teams selected the Pitagone F18 and developed tailored layouts that accounted for the available space, operational requirements and anticipated direction of vehicle attack.
The Pitagone F18 is a portable, modular HVM system capable of stopping a 7,200kg truck travelling at 48km/h. Rated for both impact protection and VADS, it provided a comprehensive solution that could be assembled and deployed rapidly.
All 176 units were delivered on stillages to a central preparation point on Parliament Street, which closed prior to the other locations. Trained operatives removed the units and assembled them into configurations of four for delivery. The Pitagone F18 units were then loaded onto tail-lift vehicles and transported to Westminster Bridge, Parliament Square and Tower Bridge, where they were connected into configurations of eight before being positioned. This enabled the roads to remain open for as long as possible before deployment.
Combining specialist HVM knowledge with an experienced deployment team and suitable vehicles allowed the units to be moved and positioned efficiently within the restricted timeframe. The tailored layouts also incorporated designated emergency access points, providing operational flexibility while supporting the agreed emergency access arrangements.
Through close collaboration and careful planning, 176 Pitagone F18 units were successfully deployed across Westminster Bridge, Parliament Square and Tower Bridge. The collaborative preparation and rapid deployment approach ensured minimal disruption across the capital by allowing roads to remain operational for as long as possible. Emergency access was maintained throughout, helping to ensure the event could take place safely and efficiently. The project demonstrated how specialist HVM expertise, a flexible solution and an experienced deployment team can work together to provide robust protection while minimising disruption in a complex central London environment.
“This project required a robust HVM solution that could be deployed quickly and flexibly across three central London locations. The Pitagone F18, supported by our trained teams, tail-lift vehicles and extensive deployment experience, enabled us to provide the required protection while minimising disruption and maintaining emergency access throughout the event.”
Lee Wilkinson, Events Traffic Manager, BUKO Traffic & Safety