The Challenge: Protecting a 50-Metre Excavation at Hinkley Point C

Hinkley Point C, in Somerset, is the first nuclear power station to be built in the UK in over 20 years. Once complete, it will provide low-carbon electricity for around six million homes and is the first in a new generation of UK nuclear power stations.

It is one of the largest and most complex projects in Europe, with more than 4,000 workers on site. Millions of cubic metres of earth will be moved and three million tonnes of concrete poured during construction.

Kier BAM Joint Venture, responsible for earthworks, site preparation and infrastructure, needed to protect the edge of a 50-metre excavation during construction of the reactor, preventing site vehicles from driving into it in error. It also needed clear separation between the construction areas and the routes used by pedestrians and vehicles.

MASS barriers and concrete barriers protecting workers in a deep excavation at Hinkley Point C

MASS barriers and concrete barriers protecting workers in a deep excavation at Hinkley Point C

The Solution: Fleximax, REBLOC and MASS

The unique Fleximax high containment vehicle restraint system was installed around the edge of the excavation. Fleximax is an engineered Maxibloc barrier with steel hinges, allowing it to follow tight radiuses and angles – a key requirement on this site.

A REBLOC RB140SFS_5.5 permanent concrete barrier was also installed to protect the workforce from deviating vehicles in certain areas. Both systems are tested to very high containment (H4a), proven to contain a 30-tonne HGV travelling at up to 65km/h at a 20-degree impact angle.

Edge protection around a large shaft excavation at Hinkley Point C

Edge protection around a large shaft excavation at Hinkley Point C

Clear Pedestrian and Vehicle Routes Across the Site

MASS barriers with Pedestrian Guard fencing were installed across the site, creating clearly marked walkways and vehicle routes for staff and visitors. The highly visible red and white steel barriers separate the construction areas while protecting the workforce, drivers and pedestrians from errant vehicles. If a vehicle drives onto the base of the system, its weight helps to stabilise the barrier during impact.

To date, more than 10,000 metres of MASS barrier have been installed at Hinkley Point C.

Concrete barriers protecting the edge of an excavation as plant works on site

Concrete barriers protecting the edge of an excavation as plant works on site

The Outcome

In place since 2018, the barriers have created a safe working environment with clearly defined work, vehicle and pedestrian zones across the site. Hardstaff is proud to support a project that will make a major contribution to reducing the UK’s carbon emissions.

Kier BAM’s site agent explained why a bespoke system was needed around the Heat Sink, the deepest part of the excavation.

“This section, with a difference in height of up to 30 metres, will hold the cooling water inlet and outlet systems. The crest alignment didn’t allow any of the standard vertical concrete barrier systems to be used. Hardstaff developed flexijoints to adapt to this intricate alignment and engineered, fabricated and delivered the Fleximax system, maintaining the containment levels required for edge protection.”

Pablo Alaman, Agent, Kier BAM Joint Venture

Key Facts

  • The first new nuclear power station in the UK for over 20 years, powering around six million homes
  • More than 4,000 workers on one of Europe’s largest construction sites
  • Fleximax high containment barrier installed around the 50-metre excavation
  • Over 10,000 metres of MASS barrier creating pedestrian walkways and vehicle routes
  • REBLOC RB140SFS_5.5 protecting the workforce from deviating vehicles

Hardstaff has also supported the Hinkley Point C Park and Ride – read our Multibloc TVCB Hinkley Point case study.

Published on: 21/05/2020