The A27 Shopwyke project, completed in May 2024, involved installing a concrete barrier to protect the piers of a footbridge at the edge of a busy roundabout. Hill & Smith Infrastructure was awarded the contract, another successful project for long-standing client Newton & Frost.
The scheme presented some very specific challenges, which all partners overcame through meticulous planning and collaborative working.

A27 at Shopwyke, with the footbridge and the new concrete barrier protecting its piers
The site, on the edge of a busy roundabout, needed careful consideration of existing footpaths. The layout had to keep pedestrian access open, without obstructing the paths during or after installation.
The eastern and western verges each had their own requirements:

A27 Shopwyke junction with concrete barrier at the edge of the carriageway
Through collaborative working and Hill & Smith Infrastructure’s end-to-end delivery, from initial barrier drawings through to installation, the team developed a range of solutions to the scheme’s challenges.
The solution used the RB185 REBLOC barrier. It is the world’s first extensively tested, fully EN 1317-compliant precast concrete safety barrier with the highest containment level, H4a, and a working width of W1. The RB185 also has a vehicle intrusion rating of VI2 and needs a footprint of just 0.8 metres.

Concrete barrier protecting a footbridge pier on the A27 at Shopwyke
Input from the Hill & Smith Infrastructure drawing office and technical department was crucial in tailoring the solution. The barriers were designed shorter, at 2.33 metres long with extended couplers, to follow the curved radius and allow more room for movement and turning.
Hill & Smith Infrastructure invested significant time from the outset, including several meetings and involvement at the design stage, which helped the client avoid unnecessary costs and delays:
The work was completed over two visits, with the concrete units installed first, followed by the steel barrier on the western verge.
The A27 Shopwyke project shows the value of tailored solutions and careful planning for complex sites such as busy roundabouts and structures with very limited space for protection. Find out more about our work in the highways sector.
Newton & Frost were pleased with the result:
“We are extremely pleased with the results of the recent project completed by Hill & Smith Infrastructure. The meticulous planning and bespoke design of the RB185 REBLOC barrier ensured that the installation was both efficient and effective. The collaboration between Hill & Smith Infrastructure and all partners was outstanding, and the final installation exceeded our expectations.”
Phil Jones, Estimator, Newton & Frost
“We are proud to have successfully completed this project with efficiency and precision. Our end-to-end delivery, coupled with the outstanding collaboration between Hill & Smith Infrastructure and our partners, ensured a seamless and successful installation. We are delighted that our efforts resulted in a highly satisfactory outcome for our client, demonstrating our commitment to excellence and innovation in road safety solutions.”
Sarah Compton, Highways Account Manager, REBLOC